Leucadia Streetscape Construction on North 101: Shop Access

October 8, 2026

"Up close and personal." Dan Nutter, the City of Encinitas engineering director, used that phrase in late July for the sidewalk and road work coming to the businesses on North Coast Highway 101 between Jupiter Street and La Costa Avenue. He was describing the final phase of Leucadia Streetscape Segment C. The phrase also explains why this fall may be harder on the north end than the two and a half years of trenching before it.

Most of the heavy work happened out in the middle of the road. The work left now happens at the front doors.

The pipes are in. The rest happens at the curb.

Construction on the Jupiter to La Costa stretch started in March 2024. In June 2024 the City Council added funding for 60-inch drainage work and pushed the completion target to summer 2026. By late July, the city expected Segment C to wrap up in October. The city's drainage project page, updated September 17, now says "late Fall 2026."

That same September update shows what is already done. The 60-, 66- and 36-inch storm drain pipes are in. Cleanout boxes, laterals, inlets, water service and main work, sidewalks, curbs, gutters and driveways are still in progress. Every item on that second list sits along the edge of the road, where a bike shop entrance or a walk-up coffee window meets the street.

The August 26 City Council presentation lists the final work items in plain terms:

  1. Finish the two roundabouts
  2. Complete utility connections on the west edge of the project
  3. Install 116 trees
  4. Install 45 streetlights
  5. Install irrigation and mulch in the landscaped areas
  6. Lay final asphalt, signs and striping from La Costa to Jupiter

The roundabout at Jupiter is consistent across city documents. The August presentation and the Segment C FAQ put the second one at Grandview Street. The city's capital-projects page lists it at Moorgate Road, a short distance away. Expect a roundabout near Grandview either way.

How the July layout routes you to each door

The newest traffic plan on record is a July 29 slide in that August presentation. It may have changed since, so treat it as a guide rather than a live map. Southbound through traffic stays in the median lane between La Costa and Jupiter. From La Costa down to Grandview, the western lane serves only private driveways. South of Grandview, an opening into the western lane gives access to local businesses. Openings are at Grandview and Avocado, and traffic merges back into the median lane at Avocado and at Jupiter.

These are the places named in this summer's construction coverage, from north to south:

  • Leucadia Donut Shoppe, 1604 N. Coast Hwy 101. Owner Tom Chu told The Coast News that northbound customers were driving past and continuing to La Costa Avenue to make a U-turn.
  • Leucadia Cyclery, 1560 N. Coast Hwy 101. Owner Jeff Schade told NBC San Diego that turning and parking conditions made the shop hard to reach.
  • The Leucadian, 1542 N. Coast Hwy 101. Co-owner David Shapiro said the loss of street parking has discouraged customers from booking events.
  • Sip-N-Sea, 1488 N. Coast Hwy 101. A coffee and açaí shop where customers order at a walk-up window out front. Owner Giuseppe Georgees said he still did not know how customers would reach the business once construction got to his storefront.

Nikolas Harth, co-owner of Surfhouse Hotel and Coffee Coffee, also on North 101 in Leucadia, was quoted in the same Coast News story. All of these reports date from late July and early August. Nothing published since September 1 confirms the current status of any individual shop. Check hours before you go, especially at the walk-up spots.

Why the U-turn matters more than it sounds

On a corridor with a single through lane in each direction, the nearest legal turnaround decides whether a five-minute coffee stop stays a five-minute stop. Stacy Reddell, executive director of the Leucadia 101 MainStreet Association, told The Coast News that the lack of a closer U-turn had inconvenienced customers and significantly affected businesses along the corridor. Nutter said the city planned to add signs pointing pedestrians to designated crossings and showing drivers where U-turns are allowed. No source since September 1 confirms that those signs are up.

The pedestrian picture was harder still. Schade described the edge of the road in front of his shop as "a strip of cracked-up asphalt." He put out A-frame signs as a buffer, and several were hit by passing cars. He also added flashing bike lights and LED lighting along his eaves because the stretch between The Leucadian and Avocado Street had no streetlights. After Georgees saw a customer and a dog nearly hit outside Sip-N-Sea, the city put orange barricades in front of the shop.

If you walk or ride this stretch after dark, those 45 streetlights on the remaining-work list matter more than any other item on it.

The storefront phase is the expensive one

Reddell surveyed 20 businesses on the corridor and found sales had fallen an average of 25% to 40% over the past year. Those losses came while most of the digging was still out in the road. The final phase brings the work to the doorways.

Kevin Doyle, treasurer of the MainStreet association and a former city planning commissioner, explained the worry in terms of foot traffic. "My big concern right now is we're going to shut those businesses down for three to six months, and most of them won't make it," he told The Coast News. Georgees said he had been told the city would board up his building, and that a city representative had once told him trenching outside his shop would begin in November 2025.

The city's account is different. Nutter said the project was only about a month behind schedule, which he called "pretty darn good" for work of this size. The city has also committed to monthly in-person meetings, e-blasts, door hangers, business canvassing and monthly drone footage. The September drainage update says access to businesses will be maintained and asks the public to keep supporting Leucadia businesses during construction.

The owners and the city agree on the basic timing. The underground work is done, and the curb work is now reaching each storefront one by one. For the person deciding where to buy coffee, the useful takeaway is that the next few months are the stretch the shops most need regulars to keep coming.

What the finished block is designed to do

The Segment C FAQ describes the finished street. It will have parking on both sides of the highway, a green buffered bike lane, wider sidewalks, landscaped medians, streetlights, better crosswalks, and a signalized pedestrian crossing at Avocado Street. Along the corridor, the city also plans parking-assist lanes that delivery vehicles can use. The August presentation adds west-side sidewalk, lighting, tree and irrigation work, and seven NCTD bus shelters.

Several of those features address the specific complaints from this summer. Parking on both sides responds to Shapiro's lost event bookings. The Avocado signal and new crosswalks respond to the near-misses. The streetlights cover the dark block Schade lit with his own LEDs. The drainage underneath matters as well. Harth said his hotel has taken in eight to ten inches of water in a ground-floor room during past storms, and he supports the drainage upgrades.

Where Segment C sits in the longer corridor plan

Doyle noted that the Streetscape was first proposed in 2008 and might have been finished more than a decade ago had construction started as planned in 2010. Parts of it are already complete. Segment A2, from Marcheta Street to Basil Street, was finished in August 2022. Pedestrian signals at Diana Street and North Court went in by January 2023, and interim striping from Basil to La Costa was finished in August 2023. Segment A1, from A Street to Marcheta, and the final version of Segment B, from Basil to Jupiter, have preliminary designs but no construction funding yet.

So once the roundabouts open and the final striping is down, the north end will be the most complete stretch of the corridor. It will be paved and planted, while the blocks to its south are still waiting their turn. As of the city's September 17 update, no date has been announced for final paving, the roundabout openings, or a ribbon cutting. The target is still late Fall 2026.